A plumbing rough-in is all the water, drain, and vent piping that goes inside your walls and under your floors before they get closed up. Once the drywall is on, you’ll never see it again, so it pays to get it right, and inspected, the first time.
Rough-ins are where permits and code matter most, and that’s our bread and butter. Baethke Plumbing is a City of Chicago licensed plumbing contractor (#SBC134156) and a State of Illinois licensed plumbing contractor (#055-004154), and we’ve completed more than 250,000 plumbing jobs across Chicago and the nearby suburbs. We’ve also been called in to clean up after rough-ins done without a permit, so we know exactly where remodels go off the rails.
Today we’ll explain what actually constitutes a rough-in, how it’s different from trim plumbing, when the inspection happens, and why skipping it can come back to haunt you when you sell.
A plumbing rough-in includes the water supply lines, drain lines, and vent pipes that run inside walls and under floors. It happens after demolition and before drywall, tile, or flooring go in, and in Chicago it must pass inspection before the walls are closed. The visible fixtures, faucets, and shutoff valves installed afterward are called trim, or finish plumbing.
What Is Included in a Plumbing Rough-In?
A rough-in covers everything behind the finished surfaces of your home:
- Water supply lines that bring hot and cold water to each fixture
- Drain lines that carry wastewater away
- Vent pipes that let your drains flow freely and keep sewer gas out
- Stub-outs, the short pipe ends left sticking out of the wall where fixtures will connect
“The rough-in is all the piping inside the wall or under the finished floor,” says Isaac, a licensed Baethke plumber. “Everything the typical homeowner can’t see.”
Rough-in plumbing before.
Trim after, in the process of being completed.
What Happens During a Plumbing Rough-In for a Remodel?
Most rough-ins we do are part of a kitchen or bathroom remodel, and they usually start with demolition.
Step 1: Open the Walls
If you want to swap a single sink for a double vanity, move your shower to the other side of the bathroom, or relocate the toilet, the walls and sometimes the floor have to come out. That’s the only way to reach the existing piping.
Step 2: Remove and Reroute the Old Piping
Once the walls are open, our plumbers can see the existing rough-in. We cut out what no longer fits the new layout and run new water lines and drain lines to the exact spots where your new fixtures will go.
Step 3: Pass the Rough-In Inspection
Before anything gets covered up, a city inspector checks the work. Only after it passes do the walls close and the finishes go in.
What Is the Difference Between Plumbing Rough-In and Trim Plumbing?
Rough-in plumbing is the hidden piping inside your walls and floors. Trim plumbing, also called finish plumbing, is everything you see and touch once the remodel is complete.
After the drywall, tile, and other finishes are in place, our plumbers return to the stub-outs left during the rough-in. We install the fixture shutoff valves, like the one behind your toilet, and then the final fixtures: faucets, shower handles, toilets, and sinks.
Here’s how the two stages compare:
Which Projects Need a New Rough-In?
Any project that changes where water comes in or drains out needs new rough-in work. Common examples include:
- Turning a single sink into a double vanity
- Moving a toilet, shower, or tub to a new spot
- Adding a bathroom, half bath, or wet bar
- Relocating a kitchen sink or adding an island sink
Costs range from about $1,000 for a simple change to $30,000 or more for a new bathroom. If your fixtures are staying in the same place, you may only need trim work, which is usually faster and less expensive.
Does Rough-In Plumbing Need an Inspection?
Yes. Rough-in plumbing must be inspected before the walls are closed. The inspection is typically included in the cost of the permit, and as the contractor, we schedule it as soon as the rough-in is complete.
What the Inspector Checks
During a rough-in inspection, the inspector looks at the work while every pipe is still exposed. That typically includes pipe sizes and materials, the slope of the drain lines so water flows the right way, proper venting, and secure connections. Many inspections also include a test of the system to check for leaks before anything is covered up.
Why Skipping the Inspection Is a Costly Mistake
We’ve walked into homes where someone added a bathroom without a permit or an inspection, and we’ve seen jobs where work continued even after a failed inspection. Both cause real problems.
The biggest one usually shows up when you sell. If you bought a three-bathroom home and it now has four, buyers, inspectors, and the city will want to know what happened inside those walls. Without a passed rough-in inspection, no one can say whether the hidden piping was done correctly, and you may be required to open the walls or even tear the work out.
Our advice is simple: never close a wall before the rough-in passes inspection.
How Do You Know Your Plumbing Rough-In Was Done Right?
Ask your plumber three questions before the walls close:
- Was a permit pulled for this work?
- When is the rough-in inspection scheduled?
- Can I see the inspection result before the drywall goes up?
A licensed plumber will have clear answers to all three.
Build Your Remodel on a Solid Plumbing Rough-In
The rough-in is the part of your remodel nobody sees, and the part everything else depends on. It has to pass inspection before your walls close, no exceptions. A remodel comes with plenty of stress. The pipes inside your walls shouldn’t add to it. If you remember one thing, make it this: ask every contractor you’re considering whether they’ll pull a permit and schedule the rough-in inspection. Anything less than a confident yes is your cue to keep looking.
There’s a reason Chicago homeowners give us 4.7 stars on Google. We’ll tell you straight what your project needs, and you’ll see the price before we pick up a tool. If you’re still in the dream stage, give us a call. We’ll start with a phone consultation to point you in the right direction and give you some budget ideas.
Got a kitchen or bathroom project coming up? Talk to Baethke Plumbing about your remodel, and we’ll take care of the rough-in, the permit, and the inspection so you don’t have to chase any of it.
Set Up Your Consultation Today
About the author: John Baethke
What Chicago Homeowners Ask About Plumbing Rough-Ins
What does rough-in plumbing mean?
Rough-in plumbing is the stage when new water, drain, and vent pipes are installed inside open walls and floors, before drywall goes up and before fixtures like sinks and toilets are connected.
What is a toilet rough-in measurement?
It’s the distance from the finished wall to the center of the toilet’s drain. Most toilets use a 12-inch rough-in, though 10-inch and 14-inch sizes also exist, so measure before you buy a new toilet.
How long does a plumbing rough-in take?
A typical rough-in for a bathroom or kitchen remodel takes just a couple days, plus time for the city inspection before the walls can be closed.
How much does plumbing rough-in cost in Chicago?
Rough-in plumbing in Chicago typically ranges from about $1,000 for a simple change, like switching from a single sink to a double vanity, to $30,000 or more for adding a new bathroom where there wasn’t one before. The final price depends on how many fixtures are involved and whether old piping needs to be removed and rerouted.
What happens if my plumbing rough-in fails inspection?
Your plumber corrects the items the inspector flagged, and a reinspection is scheduled. The walls have to stay open until the rough-in passes, so a failed inspection usually means a delay in work.